SAVANNAH DEVELOPMENT UPDATE

KEY POINTS

  • Mining contractor, Barminco, has safely completed the development drive intersecting the Savannah North ventilation raise.
  • This lateral development work was completed safely, in-line with budget and ahead of schedule.
  • Raise bore contractor, RUC Mining, has mobilised to site and is in the process of setting up.
  • Back-reaming of the ventilation raise is expected to commence mid-October and scheduled for completion late in the March 2021 quarter.
  • Barminco is now focussed on development to open up additional working levels in Savannah North