Raise bore contractor, RUC Mining, has successfully established the reamer head at the 1675 RL development drive which intersected into the FAR #3 Raise.
Back-reaming of the ventilation raise has now commenced and scheduled for completion late in the March 2021 quarter.
Barminco is now focussed on development to open up additional working levels in Savannah North.