Savannah Re-Commissioning Update
1st concentrate shipment scheduled for early February 2019
Highlights
- Mining - ramp up to full production continues
- Processing - process plant achieved plus 2,000tpd throughput in early January
- Wyndham - trucking of concentrate to the port has commenced
- Tailings - 3m wall lift on storage facility completed
- Ventilation - pilot hole for the 900m raise-bore completed
- Recruiting - onboarding of site personnel well advanced in a challenging market
- Project Financing - $40 million project loan drawn down to $28.5 million
- Revenue - first ship scheduled for early February 2019
|
|