Updated FY20 Production Guidance
Summary
- Updated FY20 production guidance driven by expected mining contract equipment and personnel mobilisation timing, and further required mine scheduling changes in Savannah remnant ore.
- Savannah North remains on schedule for first stoped ore in the current quarter and ramp-up of ore volumes through calendar 2020.
- Panoramic assessing funding options including options that do not include raising additional equity capital, and potential change of control transaction discussions continue.
|
|